Environmental Performance 1997-2001 |
||||||||
|
PDO's Environmental Performance is measured through the CEPI (Composite Environmental Performance Indicator). CEPI is the weighted average of 14 individual Environmental Performance Indicators
(EPIs). The weighting factor illustrates the relative importance of each EPI for PDO. Actual and target values as well as a short descriptions of the EPI's is given below. Click here for more details on CEPI
or contact MSE/25. |
||||||||
|
Corporate Environmental Performance Index: "Date" |
||||||||
| EPI | description | Weighting Factor | actual 1997 |
actual 1998 | actual 1999 |
|
target 2001 |
|
| 1 | % produced water disposed / injected with permit |
|
|
|
|
67.8 | 94.63 | |
| 2 | % associated gas utilised |
|
|
|
|
89.32 | 91.28 | |
| 3 | % flares meeting smoke limit of Ringelmann number <1 |
|
|
|
|
31 | 38 | |
| 4 | concentration of dispersed oil in aqueous effluent discharged (mg/l) |
|
|
|
|
13 | 15 | |
| 5 | Number of oil / water spills |
|
|
|
|
541 | 504 | |
| 6 | % halon remaining in inventory |
|
|
|
|
12 | 2 | |
| 7 | % CFCs remaining in inventory |
|
|
|
|
33 | 23 | |
| 8 | % hazardous waste disposed of with permit |
|
|
|
|
100 | 100 | |
| 9 | % tankers loading with segregated ballast tanks |
|
|
|
|
83 | 95 | |
| 10 | % chemicals in use with a 'Safe Handling of Chemicals' card |
|
|
|
|
|||
| 11 | energy (MJ) used in drilling, seismic and production operations per BOE gross production |
|
|
|
|
|||
| 12 | % oil recovered from oil spills and returned to the crude oil system |
|
|
|
|
|||
| 13 | volume (m3) of water based mud disposed of on surface per 1000 m drilled |
|
|
|
|
|||
| 14 | volume (m3) of water based drilling cuttings disposed of on surface per 1000 m drilled |
|
|
|
|
|||
|
|
|
|
|
|||||