You seem to be using an unsupported browser
You can continue browsing, but please use a supported browser to improve your experience.
Got it
Turn on more accessible mode
Turn off more accessible mode
Sign In
e-services
PDO Mail
PDO Staff
Flight Schedule
PDO Self-Service Password Reset
home
careers
contact
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
youtube
youtube
linkedin
instagram
facebook
Home
HSE Policy
Corporate HSE Business Plan
IFADAH
Golden Rules
Life Saving Rules
Page Content
2024 Second Alert HiPo#27 Dropped tubing while RIH
At around 03:42 hrs. the operation was RIH, While picking up the 1st 2^(7/8) joint from the catwalk with an on/off tool to retrieve the packer, the crew used the 3^(1/2) elevator without crossover attached ( it was available in rig floor and disconnected during POOH without proper communication with crew ). As a result, the TBG fell approximately 6mtrs on to the rig floor where the floor man was standing in a safe position at the corner of rig floor away from the LoF.
Driller / AD must ensure to install Crossover with the 2^(7/8) TBG while lifting with 3 ½ elevator. Driller/AD must ensure to communicate clearly and stay attentive to your task. RM/NTP must ensure to check and review the equipment before starting the job. The Crew must ensure to Stop and intervene for any unsafe acts/conditions. The Crew must ensure to follow Musta’ed 7 steps. Always ensure to install Crossover with the 𝟐^(𝟕/𝟖) TBG while lifting with 3 ½ elevator..
NTP and AD failed to ensure that crossover was attached with TBG while lifting with 3 ½” elevator. Traveling block was operated in a moderate speed by AD. Inadequate intervention was there within the crew, prior using the elevator without crossover.
Category:
Second Alerts