2021 2nd Alert HiPo41 Crane boom came in contact with overhead power line
At 17.15 hrs, the crane operator moved his crane with the raised boom to offload a 20 ft container from the trailer (the trailer was parked outside the Rig 38 rig pad). While positioning the crane, the wire ropes (32 mm x 9m) attached to the crane hook block made contact with the overhead powerline, which was passing in the vicinity.
Always ensure boom of the crane is lowered and slings are removed during moving of the crane. Always operate the crane after receiving the signal from banks man. Always ensure all rig move team participates in TBT and on-site supervision is provided. Always ensure equipment are spotted away from vicinity of overhead powerlines. Always ensure out of site register is updated with rig move activities. Always maintain safe clearance from Over Head Lines