You seem to be using an unsupported browser
You can continue browsing, but please use a supported browser to improve your experience.
Got it
Turn on more accessible mode
Turn off more accessible mode
Sign In
e-services
PDO Mail
PDO Staff
Flight Schedule
PDO Self-Service Password Reset
home
careers
contact
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
youtube
youtube
linkedin
instagram
facebook
Home
HSE Policy
Corporate HSE Business Plan
IFADAH
Golden Rules
Life Saving Rules
Page Content
2024_ Second Alert_HiPo#07_DROPs pipe from elevator
While Picking up the 3rd joint of 2-7/8” HT PAC pipes from the mouse hole using the 2-7/8” center latch drill pipe elevator and at about 20cm above the mouse hole, the Drill pipe joint slipped through the elevator bore and fall back inside the mousehole.
Always inspect and perform dimensional check prior to start the job including 3rd party equipment Always involve the Rig Manager and DSV for callout review and whenever there is unclarity Always ensure to have SOP for handling 2 7/8 PAC pipe. Always ensure to conduct an effective 7 steps of Musta’ed Always perform dimensional checks, and use proper tools for handling 2 7/8” PAC Pipe
Center latch elevator was sent to rig site as per callout, without the right handling tools for 2-7/8” HT PAC pipe. Driller raised concern of missing lifting sub while Rigging up to Night Tool Pusher, however they missed to escalate the matter to the next level SOP was not available for handling 2 7/8 PAC pipes. The elevator was checked physically on joint and was holding, however the dimensional check of 2 7/8” tool joint OD was not done