2015 - LL16-AIPS#2-Tier1 - Musalam Leak
Relief pit overflowed and compromised bund integrity, released gross liquid to environment.
Ensure low priority alarms are reviewed on SCE
. Review all alarms which are prioritised low on safety critical equipment (SCE) . Review all modular projects in compliance with DCAF and GU-611 . Ensure DEP is minimal for all projects, verify this is sufficient to your project requirements. .........