Sign In
2020 2nd alert HiPo#14 (Released Energy) Welding at live well head
During a routine site visit by a Operator on 05th March 2020 at 17:00 hrs., observed that a mechanical crew were welding on the beam pump base (Gravel Pan) whilst the pump was in operation. The operator intervened and stopped the activity after inspecting the permit which had no well number mentioned, stopped the activity and returned to suspend the permit. The operator reported the incident as a near miss.
Always ensure the activity is planned w.r.t people , procedure and permits. Always ensure specific permit for carrying out the task. Always ensure proper communication between departments. Always ensure the hazards are identified, assessed for possible consequences. Always respect the intervention and stop the work if feels unsafe.

Category:Second AlertsDocument Type:Safety
Format:.pptxViewers:9
Download: